Fields

The Fields group maps note properties to the things the Gantt needs. Each picker resolves against your own properties, and every field can be left blank — when it is, the Gantt uses the default noted for it.

In companion mode (TaskNotes installed) that's true even of the dates: leave Start / End blank and they default to TaskNotes' scheduled / due. In standalone mode there are no such defaults — map a start and end date property yourself, or every task comes through dateless and renders as a placeholder bar piled at today (until you turn off Show tasks with no dates).

Task Name Property

The property used as a bar's label. Leave blank to use the file name.

Start Date Property

The property that supplies each bar's start. Leave blank to use TaskNotes' scheduled. You can also pick any TaskNotes date field, or (standalone) any date property on your notes.

End Date Property

The property that supplies each bar's end. Leave blank to use TaskNotes' due.

Parent Property

The property that links a task to its parent for standalone / Base-derived parent/child roll-up. Leave blank for no roll-up. Optional.

Companion mode uses TaskNotes' own relationships

When TaskNotes is installed, nesting comes from TaskNotes' projects (subtasks) relationships — so this Parent Property has no effect in companion mode. It's for the standalone (Bases-only) hierarchy.

Status Property

The property whose value colors bars By status. Leave blank and, in companion mode, it resolves to whichever status property TaskNotes reports — blank means use the TaskNotes default, not no property. Standalone, a blank mapping has nothing to resolve to and status coloring is off.

A blank mapping resolves only for a field TaskNotes actually reports. Where it reports none, the mapping stays blank and behaves as though nothing were mapped; map the property explicitly in that case. If bars still don't colour, see No status or priority colors. Needs the TaskNotes companion palette to color; see Appearance → Bar fill.

Priority Property

The property whose value colors bars By priority. Leave blank and it resolves to TaskNotes' configured priority property in companion mode, exactly as Status Property does above.

Calendar Property

The property holding a wikilink to a calendar or calendar-set note, which is how a task gets its working time — the days it may be scheduled across. Leave blank for no calendar; the task then has no non-working days of its own, so Working days and Split segments do nothing for it. Optional.

Nothing flags the task when its value does not resolve to a calendar or calendar-set note — for instance a link to a deleted note, a note that is neither, an invalid calendar note, or a value that is not text at all (a number or a checkbox). That task schedules exactly as if this property were blank.

Stretching and shading are read from different places. A task's own association — this property — is what decides whether that task stretches or splits. Shading depends on whether you have used Select calendars…:

  • Until you make a selection (the default), the chart shades the union of the calendars your tasks are associated with — so mapping this property is enough to get shading. That union is chart-wide, while a bar splits only on its own calendar, so the two can already differ: give two tasks different calendars and each bar runs straight through the days that only the other's calendar blocks. Days both calendars block still split both bars.
  • Once you make an explicit selection, it wins for shading only: select a calendar but leave this property blank and you get shading with no stretching; associate a task with a calendar you did not select and its bar splits over days that are not shaded.

Even when the same calendar drives both, they do not cover the same days. Shading includes that calendar's events and recurring events; scheduling does not — only its non-working days and its working-pattern gaps hold a task back. An event on an otherwise working day is shaded and scheduled straight through.

Time Estimate Property

A property holding an estimate in minutes. It drives a bar's length when a date is missing, and is the write target in Property mode (below). Leave blank and, whenever TaskNotes is present (companion mode), it resolves to TaskNotes' configured timeEstimate property — regardless of the write mode. Reading the estimate for inference is always on.

Estimate meaning override

A property that lets a single task depart from the view's Estimate meaning. Its value is working-days or calendar-days; leave the property blank on a task and that task follows the view. Leave this mapping blank and no task can override.

An overridden task carries a small accent dot on its upper-left corner, and hovering it names both the interpretation in force and the view default it departs from — but only when that task also resolves to a calendar. With no calendar the span cannot re-project, so the bar renders flat whichever meaning is set, and a dot there would claim a difference the bar does not show. An override on a task with a blank or unresolvable Calendar Property is therefore silent and has no effect.

Time Estimate Update

(Companion only.) Whether resizing a bar writes the new duration back as a time estimate.

Value Behavior
Don't update (default) A resize never writes the estimate.
TaskNotes field Writes through TaskNotes' own timeEstimate field.
Property Writes to the mapped Time Estimate Property.

In Property mode with no property mapped, there's nowhere to write, so the estimate isn't updated.