Scheduling & dates¶
Each task is a bar spanning its start → end dates. This page covers how bars are placed, how you reschedule them, and how the Gantt handles tasks with missing dates.
Bars come from your date fields¶
A bar's left edge is the task's start, its right edge the end. With
TaskNotes these default to scheduled → due; map any other date field under
Settings → Fields.
Drag to reschedule, resize to change duration¶
(Companion mode — writes back through TaskNotes. In standalone mode the timeline is read-only, so bars don't move.)
- To move a task: click the middle of its bar and drag left or right. Both dates shift together, so the duration stays the same. Release to drop it — the new dates save to the note immediately.
- To change its duration: drag a bar's left or right edge. Only that end moves, so you change just the start or just the end.
Dragging a parent bar moves its whole subtree — see Parent / child roll-up.
📷 Demo image pending
A short GIF of dragging and resizing a bar will be added in a later documentation pass.
Default scale and task duration¶
- Default Scale sets the initial zoom — hours, days, weeks, or months.
- Default task duration is how long a bar is drawn whenever a date must be filled in with no time estimate to size it — a start-only, due-only, or dateless (placeholder) task.
Missing and partial dates¶
Not every task has both dates. Two Timeline toggles decide what shows:
When a date is missing, the Gantt can infer the span from a mapped Time Estimate (minutes) — see Settings → Fields. On-bar date-status indicators can flag tasks whose dates need attention; see Colors, icons & weekends.
Related settings¶
- Timeline settings — scale, duration, weekend shading, missing-date handling.
- Fields — which properties supply start/end and the time estimate.